CROCKAHENNY WINDFARM

ClientClient nameYear2024AuthorAuthor nameShare

CROCKAHENNY WINDFARM

Services:

Operational Noise Assessment

Erection of 10m met mast

Windfarm Noise modelling

Key issues:

Coordination of long term noise monitoring, extensive data analysis and reporting to ESTU-R-97 and the IOA Good Practice Guide for Windfarm Noise.

Project Description:

Amplitude Acoustics completed operational noise assessment of the 10 Turbine Windfarm in Co Donegal. This included Coordination of long term noise monitoring, extensive data analysis and reporting to ESTU-R-97 and the IOA Good Practice Guide for Windfarm Noise.

Client:

ESB

5 Comments

Leave a comment